Paradigm Enterprises, Inc.

Persimmon Creek 345kV Switchyard

Vici, OK |  North Buffalo Wind, LLC and Wanzek Construction.  

The Persimmon Switchyard is a 3 breaker ring bus designed to tie the Persimmon Wind Project to the Great Western Wind & Woodward District 345kV lines.  It an open air yard with tubular aluminum bus and steel structures.  Paradigm furnished and installed all foundations, fencing, grounding, conduits, cable trench and low voltage power & control cable.  All other material was furnished by Wanzek or the Owner and installed by Paradigm.  We worked with Wanzek’s Project Manager Jeff Herrig 701-492-1351 jherrig@wanzek.com and Assistant Project Manager Kyle Buffington 701-433-3255 kbuffington@wanzek.com