O’Donnell, TX | Stephens Ranch Wind Energy/Wanzek Construction.
This 6 mile 345kV, single circuit, double conductor line is an ongoing project which will tie the above mentioned SR II North Sub into the existing SR I Sub. The line is a concrete mono-pole, braced horizontal insulator design with an average pole height of 120’ (48,000 lbs.) and an average span of 800’. There are 5 existing power line and 7 road crossings. Nick Ibach is the Project Engineer for Wanzek Construction, 701-433-3249 nibach@wanzek.com and Lee Havig is Wanzek’s Electrical Superintendent, 701-412-7846 lhavig@wanzek.com