Paradigm Enterprises, Inc.

Persimmon Creek 345kV Transmission Line

Vici, OK | North Buffalo Wind, LLC and Wanzek Construction 

The Persimmon line is a 4.5 mile concrete mono-pole 345kV line with direct buried poles, guyed angles and bundled 795 ACSR conductor.  The line ties the Persimmon Collector Substation to the Persimmon Switchyard.  All material was furnished by Wanzek or the Owner and installed by Paradigm.  We worked with Wanzek’s Project Manager Jeff Herrig 701-492-1351 jherrig@wanzek.com and Assistant Project Manager Kyle Buffington 701-433-3255 kbuffington@wanzek.com