Elora Wind Transmission Line

Elora, TN | NextEra Eergy/Energy Erectors.  

This was a 5 mile 161kV Transmission Line in a heavily wooded area where there was extensive site work required to access the line.  The structures were steel with direct buried tangent and self-supporting angle structures on concrete piers.  Structure heights ranged from 95’ to 145’ above ground with concrete piers ranging from 9’ x 24’ to 10’ x 37’.  Our contact for the project was Project Manager Tom Wayble 702-371-9799 tcwayble@energyerectors.net.